Ameon BBC Media City

Project Title: BBC Media City, Salford

Completed: February 2010

Contract Duration: 14 Months

Client: Peel Developments

Main Contractor: Bovis Lend Lease

Contract Value: 7.3 Million

Description:

A scheme comprising of 2 No high rise apartment block for the BBC Media City Development on Salford Quays:

Services Undertaken:

  • Full contract management
  • Full design, CAD, working drawings
  • General Supply and Extract Ventilation Systems
  • Building Management System
  • Mains & Boosted Cold Water system
  • Domestic Hot Water System
  • Domestic Foul Water Drainage
  • Gravity Rain Water Drainage
  • Dry Riser System
  • Smoke ventilation Systems
  • Low Voltage Distribution
  • Small Power Installation
  • Earthing and Bonding
  • Lighting Installation
  • Lighting Control
  • Emergency Lighting
  • Fire Detection and Alarm
  • Firemans Intercom System
  • Disabled Refuge Intercom System
  • Security System
  • Telecommunications & Data Facilities
  • Works Associated with Mechanical Plant and Equipment
  • Chlorination of services
  • Flusing and water treatment
  • OMI Documention
  • Testing and commissioning of all associated services
  • Client Demonstrations