Project Title: Blackburn College Phase 2

    Completed: July 2009

    Contract Duration: 9 Months

    Client: Blackburn College

    Main Contractor: Bardsley Construction

    Contract Value: 2.8 Million

    Description:

    The construction of a 5 storey educational facility, in the heart of Blackburn town centre was completed with a fully integrated Mechanical and Electrical services installation, the building achieved a BREEAM rating of “Very Good”.

    Services Undertaken:

    • Full contract management
    • Full design, CAD, working drawings
    • GSHP installations
    • Photovoltaic installations
    • LPHW pipework installation
    • MCW AND DHW pipework installations
    • Gas pipework installations
    • Boiler plant installation
    • Hot Water plant installations
    • VRF & Air conditioning installation
    • Ventilation Supply and Extract ductwork
    • Soils and wastes
    • Sanitaryware
    • Rainwater pipework
    • Siphonic Rain water Installations
    • Rain water Harvetsing
    • Pipework and Ductwork Insulation
    • Passive Natural Ventilation Scheme
    • Under-floor heating installation
    • Specialist kitchen ventilation
    • BMS installation
    • Provision of Main Switchboard, Sub Distribution Boards
    • Main and Sub Main Cabling
    • Containment Installation-Cable Tray/Basket/Trunking/Dado & Skirting Trunking
    • Lighting Installations
    • Emergency Lighting Installations
    • Lighting Control Systems
    • General Power, Earthing & Bonding
    • Fire Alarm Installations
    • Access Control Systems, CCTV Installations, Disabled Refuge Alarm Systems
    • Induction Loop Systems
    • TV Aerial Installations
    • Data & Telephone Structured Wiring
    • Power and Control Cabling to Mechanical Services
    • Lightning Protection
    • Inspection and Testing
    • Chlorination of services
    • Flusing and water treatment
    • OMI Documention
    • Testing and commissioning of all associated services
    • Client Demonstrations