Blackpool6th

Project Title: Blackpool 6th Form College Phase 1

Completed: June 2009

Contract Duration: 12 Months

Client: Blackpool 6th Form College

Main Contractor: Bardsley Construction

Contract Value: 1.23 Million

Description:

A development of three linked, high specification teaching blocks were constructed, to bring the existing 6th Form College Campus into a new era. The new scheme produces excellent conditions for students to further develop their learning careers. The building benefits from a large proportion of natural ventilation with a BREEAM rating of “Very Good”.

Services Undertaken:

  • Full contract management
  • Full design, CAD, working drawings
  • LPHW pipework installation
  • MCW AND DHW pipework installations
  • Gas pipework installations
  • Boiler plant installation
  • Hot Water plant installations
  • VRF & Air conditioning installation
  • Ventilation Supply and Extract ductwork.
  • Soils and wastes
  • Sanitaryware
  • Rainwater pipework
  • Pipework and Ductwork Insulation
  • Passive Natural Ventilation Scheme
  • BMS installation
  • Chlorination of services
  • Flusing and water treatment.
  • OMI Documention
  • Testing and commissioning of all associated services.
  • Client Demonstrations