Ameon Carlisle College

Project Title: Carlisle College

Completed: July 2014

Contract Duration: 6 Months

Client: Carlisle College

Main Contractor: Kier (Carlisle)

Contract Value: 1.1 Million

Description of Works:

A new two storey 2900 m2, teaching facility in the centre of Carlisle to add to the facilities offered by the college campus. The building has a variety of teaching spaces including training kitchens, hair and beauty salons and general teaching spaces. The building also has a large two storey open plan café / seating area making it a welcoming teaching environment.

Services Undertaken:

  • Full contract management
  • CAD, working drawings
  • LPHW pipework installation
  • MCW AND DHW pipework installations
  • Gas pipework installations
  • Boiler plant installation
  • Chiller plant installations
  • Hot Water plant installations
  • VRF & Air conditioning installation
  • Ventilation Supply and Extract ductwork
  • Soils and wastes
  • Sanitaryware
  • Rainwater pipework
  • Pipework and Ductwork Insulation
  • Passive Natural Ventilation Scheme
  • Under-floor heating installation
  • Specialist kitchen ventilation
  • BMS installation
  • Provision of Main Switchboard, Sub Distribution Boards
  • Main and Sub Main Cabling
  • Containment Installation-Cable Tray/Basket/Trunking/Dado & Skirting Trunking
  • Lighting Installations
  • Emergency Lighting Installations
  • Lighting Control Systems
  • General Power, Earthing & Bonding
  • Fire Alarm Installations
  • Access Control Systems, CCTV Installations, Disabled Refuge Alarm Systems
  • Induction Loop Systems
  • TV Aerial Installations
  • Data & Telephone Structured Wiring
  • Power and Control Cabling to Mechanical Services
  • Lightning Protection
  • Inspection and Testing
  • Chlorination of services
  • Flusing and water treatment
  • OMI Documention
  • Testing and commissioning of all associated services
  • Client Demonstrations