bpool

Project Title: New Hub Building

Completed: July 2009

Contract Duration: 6 Months

Client: Blackpool 6th Form College

Main Contractor: ISG (Northern)

Contract Value: 0.7 Million

Description:

The Hub Building provides a combined learning resource center, refectory and student services department for the 6th form College. With a high efficiency modern 3 storey building achieving a BREEAM “Excellent” rating.

Services Undertaken:

  • Full contract management
  • Full design, CAD, working drawings
  • LPHW pipework installation
  • MCW AND DHW pipework installations
  • Gas pipework installations
  • Boiler plant installation
  • Hot Water plant installations
  • VRF & Air conditioning installation
  • Ventilation Supply and Extract ductwork.
  • Soils and wastes
  • Sanitaryware
  • Rainwater pipework
  • Rain water Harvetsing
  • Pipework and Ductwork Insulation
  • Passive Natural Ventilation Scheme
  • BMS installation
  • Chlorination of services
  • Flusing and water treatment.
  • OMI Documention
  • Testing and commissioning of all associated services.
  • Client Demonstrations