BAe warton

Project Title: Office Warton

Completed: September 2010

Contract Duration: 8 Months

Client: BAE Systems

Main Contractor: TSK

Contract Value: 2.1 Million

Description:

A Design & Build project, to the an existing three storey office, comprised of a full install of new M&E services the building approximate area 6500m2.

Services Undertaken:

  • Full Design And Procurement
  • Provision of Main Switchboard, Sub Distribution Boards
  • Provision of Transformers/HV works
  • Main and Sub Main Cabling
  • Containment Installation-Cable Tray / Basket / Trunking / Dado & Skirting Trunking
  • Lighting Installations
  • Lighting Control Systems
  • General Power, Earthing & Bonding
  • Fire Alarm Installations
  • Access Control Systems, CCTV Installations, Disabled Refuge Alarm Systems
  • Induction Loop Systems
  • TV Aerial Installations
  • Data & Telephone Structured Wiring
  • Power and Control Cabling to Mechanical Services
  • Lightning Protection
  • VRF Air conditioning installation
  • Inspection And Testing
  • 28V DC & 400Hz Installations
  • Ventilation Supply and Extract ductwork
  • LPHW pipework installation
  • BMS installation
  • Pipework and Ductwork Insulation
  • Soils and wastes & sanitaryware
  • Sprinkler installation
  • Chlorination of services
  • Flusing and water treatment
  • OMI Documention
  • Testing and commissioning of all associated services
  • Client Demonstrations