Ameon Whitegate

Project Title: Whitegate Drive PFI Blackpool

Completed: September 2009

Contract Duration: 12 Months

Client: NHS

Main Contractor: Eric Wright Construction

Contract Value: 2.31 Million

Description:

A new build PFI health centre providing excellent health care facilities for the local Blackpool residents.

Services Undertaken:

  • Full contract management
  • Full design, CAD, working drawings
  • CHP installations
  • LPHW pipework installation
  • MCW AND DHW pipework installations
  • Chilled water pipework insallations
  • Gas pipework installations
  • Boiler plant installation
  • Chiller plant installations
  • Hot Water plant installations
  • Four-pipe fancoil installations
  • VRF & Air conditioning installation
  • Ventilation Supply and Extract ductwork.
  • Soils and wastes
  • Sanitaryware
  • Rainwater pipework
  • Smoke Ventilation
  • Medical Gases
  • Compressed air installations
  • Pipework and Ductwork Insulation
  • Passive Natural Ventilation Scheme
  • Under-floor heating installation.
  • Specialist kitchen ventilation.
  • BMS installation
  • Vaccum Installaions
  • Chlorination of services
  • Flusing and water treatment.
  • OMI Documention
  • Testing and commissioning of all associated services.
  • Client Demonstrations