Saracens RFC, London

Completed: February 2013

Contract Duration: 20 Weeks

Client: Saracens

Main Contractor: Eric Wright Construction

Contract Value: 3.14 Million

Furness College, Barrow, Cumbria

Completed: May 2012

Contract Duration: 16 Months

Client: University of Cumbria

Main Contractor: Eric Wright Construction

Contract Value: 3.2 Million

Hyde Technology School

Completed: March 2012

Contract Duration: 12 months

Client: Tameside BSF Programme

Main Contractor: Carillion PLC

Contract Value: 3.7 Million

Bolton One

Completed: March 2012

Contract Duration: 12 months

Client: Eric Wright Construction

Main Contractor: Eric Wright Construction

Contract Value: 5.2 Million

Treatment Facility Samlesbury

Completed: July 2011

Contract Duration: 12 Months

Client: BAE Systems

Main Contractor: Direct for BAE

Contract Value: 1.96 Million

Office Refurbishment Warton

Completed: September 2010

Contract Duration: 8 Months

Client: BAE Systems

Main Contractor: ISG (Manchester)

Contract Value: 2.1 Million

Office Warton

Completed: September 2010

Contract Duration: 8 Months

Client: BAE Systems

Main Contractor: TSK

Contract Value: 2.1 Million

Manchester Crown Courts

Completed: July 2010

Contract Duration: 5 Months

Client: Her Majesty's Courts Service

Main Contractor: ISG (Manchester)

Contract Value: 1.8 Million

BBC Media City, Salford

Completed: February 2010

Contract Duration: 14 Months

Client: Peel Developments

Main Contractor: Bovis Lend Lease

Contract Value: 7.3 Million

Whitegate Drive PFI Blackpool

Completed: September 2009

Contract Duration: 12 Months

Client: NHS

Main Contractor: Eric Wright Construction

Contract Value: 2.31 Million

Cobbetts House Base Build

Completed: September 2009

Contract Duration: 12 months

Client: Cobbetts LLP

Main Contractor: Eric Wright Construction

Contract Value: 2.2 Million

Blackburn College Phase 2

Completed: July 2009

Contract Duration: 9 Months

Client: Blackburn College

Main Contractor: Bardsley Construction

Contract Value: 2.8 Million

New Hub Building

Completed: July 2009

Contract Duration: 6 Months

Client: Blackpool 6th Form College

Main Contractor: ISG (Northern)

Contract Value: 0.7 Million

Blackpool 6th Form College Phase 1

Completed: June 2009

Contract Duration: 12 Months

Client: Blackpool 6th Form College

Main Contractor: Bardsley Construction

Contract Value: 1.23 Million

Salford Law School

Completed: September 2008

Contract Duration: 6 Months

Client: University of Salford

Main Contractor: Bardsley Construction

Contract Value: 780K