Project Title: Chilled Water Consolidation Project

Completed: August 2013

Contract Duration: 5 Months

Client: BAE Systems

Main Contractor: BAE Systems

Contract Value: £420k

Description:

A direct works package from BAE for the design and installation of the consolidation of existing chiller plant. A group of 5 buildings had existing decentralised chiller plant serving each individual building. The scope of the project was to provide a buffer vessel and consolidate the chilled water installation into a centralised system. The aim of this project was to take advantage of load diversity within the system and provide additional resilience through the centralisation of several existing chillers.

Services Undertaken:

  • Full contract management
  • CAD, working drawings
  • Removal of existing plant and pipe work
  • Modification of existing pipe work
  • Installation of new pipe work
  • Installation of new 30,000L buffer vessel
  • Installation of new circulating pumps
  • Installation of new pressurisation unit
  • Installation of new GRP enclosure to house electrical distribution
  • New distribution board and submains
  • New power supplies to serve mechanical plant
  • Thermal insulation
  • Associated builderswork
  • Flushing and chemical dosing of LPHW installations
  • BMS installation.
  • Chlorination of services
  • Flusing and water treatment
  • OMI Documention
  • Testing and commissioning of all associated services
  • Client Demonstrations