Project Title: Chilled Water Consolidation Project
Completed: August 2013
Contract Duration: 5 Months
Client: BAE Systems
Main Contractor: BAE Systems
Contract Value: £420k
Description:
A direct works package from BAE for the design and installation of the consolidation of existing chiller plant. A group of 5 buildings had existing decentralised chiller plant serving each individual building. The scope of the project was to provide a buffer vessel and consolidate the chilled water installation into a centralised system. The aim of this project was to take advantage of load diversity within the system and provide additional resilience through the centralisation of several existing chillers.
Services Undertaken:
- Full contract management
- CAD, working drawings
- Removal of existing plant and pipe work
- Modification of existing pipe work
- Installation of new pipe work
- Installation of new 30,000L buffer vessel
- Installation of new circulating pumps
- Installation of new pressurisation unit
- Installation of new GRP enclosure to house electrical distribution
- New distribution board and submains
- New power supplies to serve mechanical plant
- Thermal insulation
- Associated builderswork
- Flushing and chemical dosing of LPHW installations
- BMS installation.
- Chlorination of services
- Flusing and water treatment
- OMI Documention
- Testing and commissioning of all associated services
- Client Demonstrations