Project Title: Office Refurbishment Warton
Completed: September 2010
Contract Duration: 8 Months
Client: BAE Systems
Main Contractor: ISG (Manchester)
Contract Value: 2.1 Million
Description:
The works consisted of a full refurbishment to the open plan office floor plate and major installation works to the second floor plantroom. All works were completed with the ground floor still in occupation and all services to the ground floor were kept live whilst works progressed.
Services Undertaken:
- Full contract management
- Full design, CAD, working drawings
- Provision of Main Switchboard, Sub Distribution Boards
- Provision of Transformers/HV works
- Main and Sub Main Cabling
- Containment Installation-Cable Tray/Basket/Trunking/Dado & Skirting Trunking.
- Lighting Installations
- Emergency Lighting Installations
- Lighting Control Systems
- General Power, Earthing & Bonding
- Fire Alarm Installations
- Access Control Systems, CCTV Installations, Disabled Refuge Alarm Systems
- Induction Loop Systems
- TV Aerial Installations
- Data & Telephone Structured Wiring
- Power and Control Cabling to Mechanical Services
- Lightning Protection
- VRF Air conditioning installation
- Inspection And Testing
- 28V DC & 400Hz Installations
- Ventilation Supply and Extract ductwork
- LPHW and Chilled water pipework installation
- Air conditioning installation
- BMS installation
- Pipework and Ductwork Insulation
- Soils and wastes & sanitaryware
- Sprinkler installation
- Chlorination of services
- Flusing and water treatment
- OMI Documention
- Testing and commissioning of all associated services
- Client Demonstrations