Project Title: BBC Media City, Salford

    Completed: February 2010

    Contract Duration: 14 Months

    Client: Peel Developments

    Main Contractor: Bovis Lend Lease

    Contract Value: 7.3 Million

    Description:

    A scheme comprising of 2 No high rise apartment block for the BBC Media City Development on Salford Quays:

    Services Undertaken:

    • Full contract management
    • Full design, CAD, working drawings
    • General Supply and Extract Ventilation Systems
    • Building Management System
    • Mains & Boosted Cold Water system
    • Domestic Hot Water System
    • Domestic Foul Water Drainage
    • Gravity Rain Water Drainage
    • Dry Riser System
    • Smoke ventilation Systems
    • Low Voltage Distribution
    • Small Power Installation
    • Earthing and Bonding
    • Lighting Installation
    • Lighting Control
    • Emergency Lighting
    • Fire Detection and Alarm
    • Firemans Intercom System
    • Disabled Refuge Intercom System
    • Security System
    • Telecommunications & Data Facilities
    • Works Associated with Mechanical Plant and Equipment
    • Chlorination of services
    • Flusing and water treatment
    • OMI Documention
    • Testing and commissioning of all associated services
    • Client Demonstrations