Project Title: Consolidation of manufacturing facilities at BAE Warton

    Completed: August 2013

    Contract Duration: 12 Months

    Client: BAE Systems

    Main Contractor: ISG

    Contract Value: 1.6 Million

    Description:

    A subcontract works package with ISG for the design and installation of support services to facilitate a new production line at BAE Warton.

    Services Undertaken:

    • Full contract management
    • CAD, working drawings
    • Provision of Sub Distribution Boards
    • Main and Sub Main Cabling
    • Containment Installation-Cable Tray/Basket/Trunking/Dado & Skirting Trunking.
    • Lighting Installations
    • Emergency Lighting Installations
    • General Power, Earthing & Bonding
    • Fire Alarm Installations
    • Power and Control Cabling to Mechanical Services
    • Inspection And Testing
    • Ventilation Supply and Extract ductwork
    • Sprinkler installation
    • Compressed Air Installation
    • Hydraulics Pipework Installation
    • BMS installation
    • Pipework and Ductwork Insulation
    • Chlorination of services
    • Flusing and water treatment
    • OMI Documention
    • Testing and commissioning of all associated services
    • Client Demonstrations